22nd May 2020
The end of this week saw level 1 poured, the ground floor drainage approved, the ground floor being backfilled and compacted, and scaffolding start to go up on the North Eastern side of the building!
​
July 2021 - Structure takes shape!
The last level 3 slab pour area, pre-pour!
Monark from a distance! The tower crane is holding up a panel up whilst the props are connected to take over and hold it up.
26th June 2020
Its good to have plenty to do on the inside of the building now that the weather has turned. Installation of the services is progressing and we are happy to have our precast concrete stairs on site, ready to be instaleld when the time is right!






Now that the ground floor is poured it can be framed out, and services can be installed.
Intumescent paint is needed on some of the structural steel in order to achieve the specified fire rating. This expands in the heat to protect the steel.
The West side balconies waiting ready to be framed out when the scaffold is up on this side.
Our precast panels range from 1.7m to 6.6m wide and are approx 3.4m high, weighing between 2300kg to 11900kg!
Our stairs have arrived! We now have all of our precast stairs on site, waiting to be installed.
The level 5 slab reinforcing is underway and getting prepped for the pour!