28 AUGUST 2020

​

The main focus of this week has been to install the base tray for the roof and to start the facade system install. Alongside this the final stairs were installed and work continued on getting the internal partitions up. Its all go!

The GIB weatherline on our wing walls has reached level 5. We can install it before the building is closed in as it is designed to be able to get wet.

The timber framing for the roof channel has begun, alongside the roof tray going down.

The lift shaft steel is now installed and ready for the base tray.

We have begun to install the spanlock facade panels (in black) on the south side of the building. 

The base layer of the roof tray is currently being installed. This will be closely followed by the vapour barrier.

In the background, our crane is installing our last staircase!

CONTACT

If you have property, development or construction needs, or know someone who does, we would be delighted to hear from you!

Chris Goldsbury

Director & General Manager

Tel: 027 675 2862

Nigel Butt

Director & Commercial Manager

Tel: 021 227 6262

hiclipart.com.png

Postal Address: PO Box 11012, Manners St 6142

MB_Logo_4Col_RGB-removebg-preview.png
BCITO_Business_qual_seal_black_300dpi_RGB-removebg-preview.png
IWD_sticker_for_web-removebg-preview.png
bottom of page