31st July 2020

The two major milestones for this week were pouring the final slab on level 6, and our steel stud partition walls getting underway. Once more steel stud has been installed we will be able to start our first fix!

Our precast concrete panels are held in place by steel brackets which are bolted onto the structural steel.

Our service risers (left) are up to level 3 now which allows each trade to start running their services up the building.

Scaffolding and temporary guard rails go in with our stairs to allow people to work safely off them.

Due to the amount of concrete needed for the floor slab it takes around 4 1/2 hours to receive all of it, place it, and finish it.

Due to the building's orientation, the east side apartments will be bathed in morning sun, and the west side the afternoon sun.

The steel stud inter-tenancy partitions continue to go in. Soon we'll install first fix services (the internal bits!) in the walls.

CONTACT

If you have property, development or construction needs, or know someone who does, we would be delighted to hear from you!

Chris Goldsbury

Director & General Manager

Tel: 027 675 2862

Nigel Butt

Director & Commercial Manager

Tel: 021 227 6262

hiclipart.com.png

Postal Address: PO Box 11012, Manners St 6142

MB_Logo_4Col_RGB-removebg-preview.png
BCITO_Business_qual_seal_black_300dpi_RGB-removebg-preview.png
IWD_sticker_for_web-removebg-preview.png
bottom of page