22nd May 2020
The end of this week saw level 1 poured, the ground floor drainage approved, the ground floor being backfilled and compacted, and scaffolding start to go up on the North Eastern side of the building!
​
July 2021 - Structure takes shape!
The last level 3 slab pour area, pre-pour!
Monark from a distance! The tower crane is holding up a panel up whilst the props are connected to take over and hold it up.
11 SEPTEMBER 2020
​
The major milestones of this week were the hoist being commissioned and the crane being dismantled and taken off site, the first glass install, and roof tray install.






A beautiful day to be a roofer! Roof tray now covers almost the entirety of the roof and is almost ready for the vapour barrier.
Our first delivery of glass! Glass is now being installed on all levels from the ground to level 3.
The team of glaziers are make installing the glass look easy, but it takes a lot of strength and precision to get each piece in.
The job is taken off the crane, lifted onto ground supports and then deconstructed.
A jibless crane!
The last fragments of the tower crane being disassembled.