top of page
22nd May 2020
The end of this week saw level 1 poured, the ground floor drainage approved, the ground floor being backfilled and compacted, and scaffolding start to go up on the North Eastern side of the building!
​
July 2021 - Structure takes shape!
The last level 3 slab pour area, pre-pour!
Monark from a distance! The tower crane is holding up a panel up whilst the props are connected to take over and hold it up.
ON SITE AT SUNSET WEST
Take a look at what's been happening on site this week!!
3 JULY 2020
The end of this week saw our level 5 slab poured, precast panels installed on the facade, further timber framing and gibbing up the building, and more services being installed in the risers. Once our West side scaffolding goes up, the West side of the building can get framed out and gibbed up too!

bottom of page